Level of Achievement with Reference to Indicators
Vietnam / Output-1
Indicators in PDM ver. 1.2 |
Level of Current Achievement |
Target in December 2015 |
1-1. Number of airports where WGS-84 data are completed |
Vietnam completed surveys at 2 airports (Hue and Phu Quoc) |
WGS-84 coordinates for all 21 airports will have been surveyed, verified and published in AIP. |
1-2. Number of PBN flight procedures that design is completed |
Design for 1 airport (Hue) has completed with 16 PBN flight procedures. |
Design for 3 major international airports and other 10 airports will be completed in accordance with Vietnam PBN Roadmap. Estimated as approx. 200 procedures for 13 airports. |
1-3. Number of PBN flight procedures that flight validation is completed |
11 PBN flight procedures for Phu Bai Airport were validated by Vietnam Airlines flight simulator. |
Approximately 200 flight procedures have to be validated by CAAV. |
1-4. Progress of development of standards for PBN operational approval |
CAAV established the standards, and issued in Regulation and Advisory Circular. Vietnam Airlines received approval of RNP10 and RNAV5/1 with B777 and Airbus Aircraft. |
All aircraft operators registered in Vietnam will have received PBN operational approval. |
1-5. Progress of establishment of PBN flight procedures |
|
|
a) Number of airports where PBN procedures are implemented |
PBN flight procedures are partially implemented at Hue Airport. |
3 Major international airports 10 other airports |
b) Number and types of PBN procedures which are implemented at airports |
4 SIDs, 6 RNAV STARS and 1 RNAV APCH at Hue Airport
|
Approximately 200 procedures (rough estimate), including RNAV1/RNP1 SIDs, RNAV1/RNP1 STARS, RNP APCH and RNP AR APCH |
c) Number of RNAV/RNP routes which are implemented for enroute |
4 RNP10 routes are implemented. |
Additional 10 RNAV5 routes |
1-6. Number of flight procedure designers capable of producing PBN flight procedures |
1 CAAV, 4 VATM, 2 ACV and 1 Vietnam Airlines are recognized as capable of conducting PBN flight procedure designs by JICAExperts. The Project will start training on advanced level design. |
4 CAAV designers can conduct oversight of flight procedure designs. 10 VATM and 3 ACV/Vietnam Airlines designers can conduct PBN flight procedure designs. |
1-7. Number of flight validation officers capable of conducting PBN flight validation |
CAAV has not assigned PBN flight validation officers. |
CAAV will have 2 PBN flight validation officers capable of conducting PBN flight validation as well as inspection (calibration). |
1-8. Number of flight standard officers capable of developing standards for PBN operational approval |
CAAV have 2 flight standard officers capable of developing and updating the standards for PBN operational approval. |
CAAV will have 4 flight standard officers capable of developing and updating the standards for PBN operational approval. |